Kitchen Remodel Timeline in South Florida, Week by Week

From the first measurement to the final inspection: what happens each week of a kitchen remodel and what causes delays.

Kitchen under renovation in a South Florida home: interior view of a room under renovation with construction materials and…

Most homeowners ask two questions about a kitchen remodel: how much and how long. The second one matters as much as the first, because a kitchen out of service changes how the whole family lives. This article lays out a realistic timeline for a kitchen remodel in South Florida, from the first visit to the final inspection, and explains what usually causes delays.

The short answer

For a typical kitchen remodel in Weston or elsewhere in Broward County, plan on roughly:

  • 2 to 6 weeks of design, selections and estimating
  • 2 to 8 weeks of permits and HOA approval (overlapping with cabinet ordering)
  • 6 to 10 weeks of construction once cabinets are ready

A refresh in the same layout can be faster; a full gut with a wall removal and custom cabinetry can take longer. The single most important scheduling decision is to order cabinets before demolition, not after.

Before construction: weeks 1 to 8

Weeks 1–2: Site visit, measurements and goals

We measure the kitchen and adjacent rooms, photograph existing conditions, check the electrical panel, plumbing access, ventilation path and the wall you may want to remove. You share how you cook, what storage you need and what frustrates you about the current kitchen.

Weeks 2–5: Layout, selections and estimate

We develop the layout and review it with you, then move to selections: cabinet style and construction, countertop material, backsplash, sink and faucet, lighting and appliances. Appliance specifications matter early — a 36-inch range, a built-in refrigerator or a vented hood changes the cabinet design and the electrical and gas requirements. The estimate is finalized as selections are made.

Weeks 4–8: Permits, HOA approval and ordering

If the remodel changes plumbing, electrical circuits, gas or walls, a permit is required. Drawings are submitted, reviewed and approved; corrections add time. If exterior work is involved — a new window or a vent through the wall — the HOA may also need to approve it. Meanwhile, cabinets and long-lead items are ordered. Semi-custom and custom cabinets commonly take several weeks to manufacture.

Your kitchen is still fully usable during this phase.

Construction: weeks 1 to 10 on site

Week 1: Protection and demolition

We protect floors and adjacent rooms, set up dust barriers, shut off and cap utilities and remove the old kitchen. This is also when we set up a temporary prep area — typically a table, a microwave, a small refrigerator and access to a sink elsewhere in the house. Demolition sometimes reveals hidden conditions such as water damage or outdated wiring; we document them and price any additional work before proceeding.

Weeks 2–3: Structural work and rough-in

If a wall is being removed, the beam is installed according to the engineering. Plumbing and gas lines are relocated, new electrical circuits and boxes installed and ventilation ducted. Rough inspections must pass before walls are closed — scheduling inspections promptly is one of the keys to staying on time.

Week 4: Drywall, ceiling and preparation

Walls and ceilings are closed, taped and finished. Recessed lighting is set, and walls are primed. If the floor is being replaced, it is installed now or after cabinets, depending on the flooring type.

Weeks 5–6: Cabinet installation

Cabinets are delivered, inspected for damage and installed level and square. This is the moment the kitchen starts to look like a kitchen again. Any filler panels, crown molding and hardware follow.

Weeks 6–8: Countertops

Stone and quartz counters are templated after cabinets are installed, because the fabricator measures the real cabinets, not the drawings. Fabrication usually takes one to two weeks after templating, then installation takes a day. The sink and cooktop are set with the counters.

Weeks 8–9: Backsplash, plumbing and electrical trim

The backsplash is installed and grouted, the faucet, disposal and dishwasher connected, outlets, switches, under-cabinet and pendant lights installed and appliances set.

Week 10: Final inspection, punch list and walkthrough

Final inspections close the permit. We walk through the kitchen with you, complete a punch list of adjustments and clean thoroughly. Then the kitchen is yours.

What causes delays

  • Late selections. Changing appliances or cabinets after ordering is the most common cause of delay.
  • Back-ordered materials. Specialty tile, fixtures or appliances can arrive late; we confirm availability before demolition.
  • Permit corrections. Incomplete drawings lead to review comments and resubmittals.
  • Hidden conditions. Water damage, termite damage or outdated wiring found behind walls.
  • Missed inspections. Every failed or delayed inspection holds up the next phase.
  • Weather and storm season. Exterior work and deliveries can be affected during hurricane season.

How to keep your remodel on schedule

  1. Make all selections — including appliances — before construction starts.
  2. Order cabinets as soon as the design is final.
  3. Confirm delivery dates for every long-lead item.
  4. Agree on how decisions will be made during construction and respond quickly.
  5. Plan your temporary kitchen and family routines ahead of demolition.

How the timeline changes by project type

  • Cosmetic refresh (new counters, backsplash, paint and fixtures, cabinets kept): often two to four weeks on site and limited permitting.
  • Same-layout replacement (new cabinets, counters and appliances in the existing footprint): typically five to seven weeks on site once cabinets arrive.
  • New layout or open concept (moving plumbing, gas or walls): typically eight to ten weeks on site, plus engineering and longer permit review.
  • Kitchen as part of a whole-home renovation: scheduled within the larger project; the kitchen is usually one of the last rooms finished because it depends on flooring, electrical and plumbing work elsewhere in the house.

Living without a kitchen: practical tips

Six to ten weeks is manageable with a little planning:

  • Set up a temporary kitchen in a laundry room, dining room or garage with a microwave, toaster oven or countertop induction burner, a coffee maker and a small refrigerator. Access to a utility sink or bathroom sink for rinsing makes a big difference.
  • Pack early and keep only the essentials: a few plates, cups, utensils, one pot and one pan.
  • Plan simple meals and use the grill. In South Florida, outdoor cooking is a realistic option most of the year.
  • Budget for eating out a few times a week; include it in the real cost of the project.
  • Agree on working hours and access with your contractor so you know when the house will be quiet and clean.

Plan your kitchen with us

We plan kitchens so the room is out of service for the shortest time possible, with consistent updates throughout. Learn about our kitchen remodeling service in Weston, FL, see a recent open-concept kitchen project, or request a consultation. If budget is your next question, our remodeling cost guide is a good place to start.